Caltrans Logo

Interstate 215 North Segments 1 & 2 - HOV and Mixed Flow Lane Addition

Description: On I-215 in San Bernardino from south of Rialto Avenue to south of Massachusetts Avenue. Construct HOV, mixed-flow lane, and auxilliary lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92405, 92410, 92411
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
 
County/State Route San Bernardino 215
Postmile Begin/End 6.5 8.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  15636    6624  
Lane Miles Added (HOV)  5.0    5  
Lane Miles Added (Mixed)  9.0    5  
Peak Period Time Savings (minutes)  1141440    162947  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Robert So (909) 383-4513   robert_so@dot.ca.gov
Design (PS&E) Phase
San Bernardino Associated Governments Garry Cohoe (909) 884-8276   gcohoe@sanbag.ca.gov
Right of Way Phase
Caltrans Robert So (909) 383-4513   robert_so@dot.ca.gov
Construction Phase
San Bernardino Associated Governments Garry Cohoe (909) 884-8276   gcohoe@sanbag.ca.gov
 
Corridor System Management Plan
Caltrans John Pagano (909) 383-6327   john_pagano@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $20,726 $20,726
CMIA
$49,120 $0 $49,120
Non-bond Funding
State/Federal*
$207,685 $-46,756 $160,929
Local**
$151,477 $-34,475 $117,002
Non Budgeted ETC
$0 $0 $0
 
Total**** $408,282 $-60,505 $347,777

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$816 $0 $816 $880
Design(PS&E)
$26,792 $0 $26,792 $24,611
Right of Way
$66,192 $40,803 $106,995 $64,294
Construction
$314,482 $-101,308 $213,174 $208,387
 
Total* $408,282 $-60,505 $347,777 $218,708

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/1992 

12/01/2005 
 

 
01/01/1992 

12/01/2005 
100  01/01/1992 

12/01/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2001 

03/01/2009 
 

 
01/01/2001 

06/15/2009 
100  01/01/2001 

06/30/2009 


Begin Right of Way Phase

End Right of Way Phase
01/01/2001 

11/01/2008 
 

 
01/01/2001 

04/01/2009 
100  08/31/2005 

01/16/2009 
-57 

Begin Construction Phase

End Construction Phase
06/01/2009 

06/01/2013 
 

 
09/15/2009 

09/05/2013 
100  08/27/2009 

09/17/2014 


-13 
Begin Closeout Phase

End Closeout Phase
06/01/2013 

07/01/2014 
 

 
09/15/2013 

09/15/2015 
100  01/16/2014 

10/03/2019 
-4 

-49 
Corridor System Management Plan
Adoption Date 06/01/2008    06/01/2008  95  07/01/2011  -37 
Implementation Date 09/01/2008    09/01/2008  08/01/2011  -35 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 15636 6624
Lane Miles Added (HOV) 5.0 5
Lane Miles Added (Mixed) 9.0 5
Peak Period Time Savings (minutes) 1141440 162947

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.